Concrete Calculator
This concrete calculator turns slab, footing, sonotube, round pad or step dimensions into cubic yards, cubic meters and bags of premix. Pick the shape, enter its measurements and how many identical pours you need. Waste is shown on its own line, and the result rounds a truck order up to the next quarter yard so you can decide between bags and ready-mix.
Concrete to order
1.36cubic yards
- Volume before waste1.23 yd³
- Waste and spillage (10%)+0.12 yd³
- Same volume in cubic meters1.04 m³
- Same volume in cubic feet36.7 cu ft
- Bags of premix, 80 lb (~0.6 cu ft each)62 bags
- Or 60 lb bags instead82 bags
- Ready-mix order (next ¼ yd³)1.5 yd³
- Bags or truck?Over ~1 yd³: get a ready-mix quote
Updated .
How to calculate concrete for each shape
Every pour is a volume: convert all measurements to feet, multiply, and divide cubic feet by 27 to get cubic yards. Inches become feet by dividing by 12, which is why a 4-inch slab is 0.333 ft thick. In metric, multiply meters and convert centimeters by dividing by 100 for cubic meters.
footing or wall (ft³) = length × width in × depth in ÷ 144
round column (ft³) = π × (diameter in ÷ 24)² × depth ft
circular slab (ft³) = π × (diameter ft ÷ 2)² × thickness in ÷ 12
steps (ft³) = width × riser ÷ 12 × tread ÷ 12 × n(n + 1) ÷ 2
cubic yards = ft³ × pours ÷ 27 × (1 + waste ÷ 100)
bags = ceil(order ft³ ÷ yield per bag)
The step formula stacks solid blocks: the bottom block runs the full length of the flight, one riser tall, and each block above is one tread shorter. Three steps therefore hold 1 + 2 + 3 = 6 riser-by-tread blocks. A top landing adds width × landing depth × total rise. This assumes solid steps on grade; if you fill the core with rubble or the steps span over a void, measure the actual concrete section instead.
Sonotube and post-hole totals surprise people because volume grows with the square of the diameter. A 12-inch tube holds 2.25 times as much as an 8-inch tube of the same depth. One 12-inch tube, 4 ft deep, is 3.14 ft³, or six 80-lb bags; a deck needing twelve of them is 1.4 yd³ before waste, which is truck territory. A dug hole without a form is usually wider at the top than the auger, so measure it.
The bag yields are approximate figures from the QUIKRETE Concrete Mix data sheet: 0.30, 0.375, 0.45 and 0.60 ft³ for 40, 50, 60 and 80-lb bags. Other brands and mixes differ slightly, so check the bag. The waste field defaults to 10%, which covers a subgrade that dips lower than planned, forms that bow under the wet weight, and what stays in the mixer or wheelbarrow. NRMCA suggests ordering 4% to 10% over the plan estimate; use the low end only on a level, compacted base with rigid forms.
Worked example: a 10 × 10 ft patio at 4 inches
The default inputs are a square patio, 4 inches thick, one pour, 80-lb bags and 10% waste.
- Volume: 10 × 10 × 4 ÷ 12 = 33.33 ft³.
- Cubic yards: 33.33 ÷ 27 = 1.23 yd³ before waste.
- Waste: 1.23 × 10% adds 0.12 yd³, for 1.36 yd³ (36.67 ft³, or 1.04 m³).
- Bags: 36.67 ÷ 0.60 = 61.1, so 62 bags of 80 lb. With 60-lb bags, 36.67 ÷ 0.45 = 81.5, so 82 bags.
- Ready-mix: 1.36 rounded up to the next quarter yard is 1.5 yd³.
Sixty-two 80-lb bags weigh almost 5,000 lb and mean about 62 mixer batches, which is a lot for one finishing window. At this size, compare the bag total with a ready-mix quote for 1.5 yd³, including any short-load fee.
Concrete slab chart: cubic yards and bags at 4 inches
Common patio, walk and pad sizes at 4 inches thick. The first volume is the exact geometric figure; the bag counts include 10% waste and round up to whole bags using the approximate 0.60 and 0.45 ft³ yields.
| Slab (ft) | Area (sq ft) | yd³, no waste | yd³ + 10% | 80-lb bags | 60-lb bags |
|---|---|---|---|---|---|
| 4 × 4 | 16 | 0.20 | 0.22 | 10 | 14 |
| 3 × 20 | 60 | 0.74 | 0.81 | 37 | 49 |
| 8 × 10 | 80 | 0.99 | 1.09 | 49 | 66 |
| 10 × 10 | 100 | 1.23 | 1.36 | 62 | 82 |
| 10 × 12 | 120 | 1.48 | 1.63 | 74 | 98 |
| 12 × 12 | 144 | 1.78 | 1.96 | 88 | 118 |
| 12 × 16 | 192 | 2.37 | 2.61 | 118 | 157 |
| 12 × 24 | 288 | 3.56 | 3.91 | 176 | 235 |
| 20 × 20 | 400 | 4.94 | 5.43 | 245 | 326 |
| 24 × 24 | 576 | 7.11 | 7.82 | 352 | 470 |
Each cubic yard covers 81 sq ft at 4 inches, 64.8 sq ft at 5 inches and 54 sq ft at 6 inches. Going from 4 to 5 inches therefore adds 25% to every row. For a driveway, multiply the 4-inch figures by 1.25 or 1.5 rather than reading the chart directly.
Bags or ready-mix: where the line falls
An 80-lb bag yields about 0.60 ft³, so one cubic yard takes 45 of them, or 60 of the 60-lb size. Under about 1 yd³, bags are usually the sensible choice: post holes, a landing pad, a small walk, a set of steps. Above that, the bag count, the 3,600 lb of material per yard, and the time to mix it all start to fight the clock, and the calculator suggests getting a ready-mix quote.
Concrete that sits too long before the next batch arrives can form a cold joint, a weak seam where fresh concrete meets material that has started to set. Quikrete’s data sheet calls for at least 1 ft³ of mixer capacity per 80-lb bag mixed at once, so the drum size sets how many bags go in each batch. Plan the crew around that rate. Between the two options, some suppliers offer mix-on-site trucks or small trailers that suit 1 to 3 yd³ jobs.
Slab thickness and gravel sub-base
Four inches is the usual thickness for patios, walks and shed pads. Driveways are commonly poured at 4 inches for cars and 5 to 6 inches where trucks, trailers or an RV will park. Local code and any engineer’s drawing take precedence, especially for footings, which are sized for the soil and the load.
Most slabs sit on a compacted layer of crushed gravel, often around 4 inches, which gives an even, well-drained bed. Estimate it separately with the gravel calculator. The finished grade of that base matters for this page too: if the gravel ends half an inch low, a 4-inch slab becomes 4.5 inches and needs 12.5% more concrete, more than the whole default waste allowance. Check depth with a string line at several points before ordering, and use the measured average thickness.
Ordering ready-mix: short loads, truck access and pumps
- Order increments: many suppliers sell in quarter-yard steps, which is why the result rounds up to the next ¼ yd³. Check yours; some quote by the half yard.
- Short-load fees: trucks carry about 8 to 12 yd³, so plants often add a fee below a minimum load. Ask for it with the quote; it can make bags competitive on a 1 to 2 yd³ job.
- Running short: a second small load costs time and another fee while the first pour stiffens. Rounding up and having a spare form ready for leftovers is cheaper.
- Truck access: NRMCA notes a loaded truck weighs about 80,000 lb and may not manage loose dirt, curbs or pathways. Where it cannot back up to the forms, budget for a line pump or a crew with wheelbarrows, and tell the plant when you order.
- Specify the mix: state the strength, slump and whether you need air entrainment for freeze-thaw exposure.
Frequently asked questions
How many 80 lb bags of concrete are in a cubic yard?
A cubic yard is 27 ft³, and an 80-lb bag yields about 0.60 ft³, so it takes 45 bags. The same yard needs 60 bags of 60 lb, 72 of 50 lb or 90 of 40 lb. Those counts assume nothing is lost, so add waste on top: with 10%, buy 50 of the 80-lb bags. Check the yield printed on your bag, since mixes vary slightly.
How many square feet does a yard of concrete cover?
Divide 324 by the thickness in inches. One cubic yard covers about 92.6 sq ft at 3.5 inches, 81 sq ft at 4 inches, 64.8 sq ft at 5 inches and 54 sq ft at 6 inches. That is pure geometry with no waste, so a 4-inch slab of exactly 81 sq ft still needs a little more than one yard once the base and forms are taken into account.
Can I mix bags myself for a 2-yard slab?
You can, but it is a big day. Two cubic yards is 54 ft³: 90 bags of 80 lb, or 99 with 10% waste, about 7,900 lb of material. With a one- or two-bag mixer that is 50 to 100 batches, and the whole slab has to be placed and finished before the first batches set. Most people price ready-mix or a mix-on-site truck at this size.
How do I estimate a slab with a thickened edge?
Calculate it in two parts. Enter the full slab at its normal thickness, then switch to footing or wall and enter the edge length measured along its centerline, its width and its extra depth below the slab. Add the two results. For a 12 × 12 ft slab with a 12-inch-wide edge 8 inches deeper, the centerline is 4 × 11 = 44 ft, so the edge adds 44 × 1 × 8 ÷ 12 = 29.3 ft³.
Why does my sonotube order need so many bags?
Because volume scales with diameter squared. A 10-inch tube 4 ft deep holds 2.18 ft³, or four 80-lb bags, while a 12-inch tube at the same depth holds 3.14 ft³ and needs six. Enter the number of tubes as identical pours so waste is applied once to the total and bags are rounded up once for the total rather than for each tube separately.
What happens if the ready-mix truck runs out before the pour is done?
You stop and wait for another load, usually a small one with a short-load fee, while the placed concrete keeps setting. If it stiffens before the next load arrives, the two batches meet at a cold joint that can crack or show. That risk is why ready-mix orders round up and include waste. Have a small form or a path to fill so any leftover is useful.
Sources and assumptions
- QUIKRETE: Concrete Mix (No. 1101) data sheet — Approximate yields of 0.30, 0.375, 0.45 and 0.60 ft³ for 40, 50, 60 and 80-lb bags, and mixer capacity per bag.
- NRMCA: CIP 31, Ordering Ready Mixed Concrete — Ordering 4–10% over the plan estimate, 8–12 yd³ truck capacity, truck weight and site access, and what to specify.
These results are planning estimates only — verify quantities with your supplier and local building code before you buy or build. See our terms of use.